Tower-A
Structure: Structure Completed along with Elevation features. MS railing and Door Frames Completed.
Interior finishes: Gypsum Plaster, POP, Kitchen Counter Fixing, Fire Fighting Pipe covering , Tile laying activities completed. Doors and Locks Installation complete.
Common Areas: Granite Flooring/ Tile Flooring in Corridors and staircases completed, SS railing in staircases installed.
Exterior : MS railing Completed. Texture Painting in progress. External Glazing ( UPVC work) Framing and shutter installed. Plumbing Shaft covering workin progress.
Mep work: Fire Fighting Pipes laid. Rising Mains and Lifts are installed.
External Development: Podium water- proofing completed. Work in progress for various elements related to external Development say Water Body, seating Alcoves etc.