Generated: 29 Oct 2026, 2:30 PM IST
Structure: Structure Completed along with Elevation features. MS railing and Door Frames Completed.
Interior finishes: Gypsum Plaster, POP, Kitchen Counter Fixing, Fire Fighting Pipe covering , Tile laying activities completed. Doors and Locks Installation complete.
Common Areas: Granite Flooring/ Tile Flooring in Corridors and staircases completed, SS railing in staircases installed.
Exterior : MS railing Completed. Texture Painting in progress. External Glazing ( UPVC work) Framing and shutter installed. Plumbing Shaft covering workin progress.
Mep work: Fire Fighting Pipes laid. Rising Mains and Lifts are installed.
External Development: Podium water- proofing completed. Work in progress for various elements related to external Development say Water Body, seating Alcoves etc.
🏗️ Completed Milestones
🧱 Structural & Exterior: The 24th-floor slab, along with the attached non-tower slab, has been successfully cast. All exterior elevation features have now been fully completed.
🏠 Interior Finishes: Gypsum plastering and kitchen counter installations are complete.
Tile laying across general flooring, walls, kitchens, and balconies has been finished, along with the corridor flooring.
🏛️ Common Areas: Granite flooring in the staircases and stainless-steel railings have been fully installed.
🔧 Ongoing Operations
🪟 Exteriors & Logistics: External glazing work is actively underway, currently focusing on framing and shutter installation.
Elevator materials have arrived on site, and installation activities have commenced.
🚿 Plumbing & Carpentry: Installation of plumbing fixtures (sinks and cisterns) and door fittings is currently in progress.
Structure: Structure Completed along with Elevation features. MS railing and Door Frames Completed.
Interior finishes: Gypsum Plaster, POP, Kitchen Counter Fixing, Fire Fighting Pipe covering , Tile laying activities completed. Doors and Locks Installation complete.
Common Areas: Granite Flooring/ Tile Flooring in Corridors and staircases completed, SS railing in staircases installed. Entry lobby work in progress.
Exterior : MS railing Completed. Texture Painting in progress. External Glazing ( UPVC work) Framing and shutter installed. Plumbing Shaft covering work in progress.
MEP work: Fire Fighting Pipes laid. Rising Mains and Lifts are installed. Basement Fire fighting work, GI line work , STP, Fire Fighting work in progress. In Electrical ( External) Transformers, DG sets, HT panel procured and installation in progress. Main LT panel under procurement.
External Development: Podium water- proofing completed. Work in progress for various elements related to external Development say Water Body, seating Alcoves etc.
🏗 Structure: 24th Floor Slab Completed; Attached Non-Tower Slab Completed; Basement Ramp Cast
🧱 Finishing: Gypsum Plaster, Kitchen Counters, Tiling (Flooring, Walls, Kitchens & Balconies), Whitewash, Corridor Flooring & Staircase Granite with SS Railings Completed; Sink & Door Fixing in Progress
🪟 Façade: Elevation Features Completed; External Glazing in Progress (Framing & Shutters)
⚙ Utilities: Earthing Completed; Lift Materials Received & Installation in Progress
🏢 Common Areas: Corridors & Staircases Fully Finished
Structure: Structure Completed along with Elevation features. MS railing and Door Frames Completed.
Interior finishes: Gypsum Plaster, POP, Kitchen Counter Fixing, Fire Fighting Pipe covering , Tile laying activities completed. Doors and Locks Installation complete.
Common Areas: Granite Flooring/ Tile Flooring in Corridors and staircases completed, SS railing in staircases installed. Entry lobby work in progress. VD flooring completed in stilt parking areas. BAsement VD flooring in progress.
Exterior : MS railing Completed. Texture Painting in progress. External Glazing ( UPVC work) Framing and shutter installed. Plumbing Shaft covering in progress.
MEP work: Fire Fighting Pipes laid. Rising Mains and Lifts are being installed. Basement Fire fighting work, GI line work , STP, Fire Fighting work in progress. In Electrical ( External) Transformers, DG sets, HT panel Procured. MAin LT panel Ordered. ESS room completed.
External Development: Podium water- proofing completed. Work in progress for various elements related to external Development say Water Body, seating Alcoves etc. Main Gate structure RCC work cast. ESS Room civil work completed..
Structural Milestone: 24th Floor Slab Completed; Attached Non-Tower Slab Completed; Basement Ramp Cast
Façade Works: Elevation Features Completed; External Glazing (Framing & Shutters) in Progress
Interior Finishing: Gypsum Plaster, Kitchen Counters, Tiling (Flooring, Walls, Kitchens & Balconies) & Whitewash Completed
Services & Utilities: Earthing Completed; Lift Materials Received & Installation Underway
Common Areas: Corridor Flooring Completed; Staircase Granite Flooring with SS Railing Completed
Final Fixtures: Sink Fixing & Door Installation in Progress
✔️ Superstructure, Plastering & Firefighting Piping— Complete
✔️ Pool Civil Work — Done. Water proofing completed. Pool Tile work in progress. Pool Plant ordered.
🚧 External Glazing & ACP Facade — Completed.
💎 Italian Flooring — 50% Completed. Tile work in progress in Toilets.
✔️Internal Finishing work in progress.
The buniyaad is strong, and the finishing touches are beginning! 🏢
Superstructure, Plastering & Firefighting — 100% Complete
✔️ Pool Civil Work — Done. MEP work in progress. Tiles under procurement.
🚧 External Glazing & ACP Facade — In Progress. Glass Facade completed.
💎 Italian Flooring —In progress. Tile laying in Toilets in progress.
Wood work / Wall finishes: Wall panelling work commenced.
• Civil works completed • Shutters fixed.
• Tile laying completed.
• Sewer LIne in front of Commercial space laid.
• Rain Water Harvesting pits 5 in No Work in progress.
• 15th floor slab completed.
• MEP WORK: Internel Plumbing ( CPVC) work in progress.
• 19th floor slab completed.
• POP work in progress at 3rd floor.
• Door Frame fixing in progress.
• MEP work: Internel Plumbing( CPVC ) in progress.
• 27th floor Terrace slab completed. Elevation features work in progress.
• MS Railing work Completed at 20 Floors.
• Door Frames fixing work in progress and completed at 20 Floors.
• Gypsum plaster in progress.
• Firefighting works in progress.
• MEP work: Internel Plumbing ( CPVC Piping) work in progress.
Structural Progress: 24th Floor Slab Completed. Work in progress at Elevation features.
Gypsum Plaster: Completed up to 18th Floor
Kitchen Counters: Completed up to 15th Floor
Flooring (Vitrified Tiles): Completed up to 20th Floor.
Wall Tiling: Completed up to 20th Floor
Toilet Tiling: Completed up to 20th Floor
External Façade: Glazing Work in Progress (Framing & Shutters)
Additional Structure: Attached Non-Tower Slab in Progress. UGT Civil work Completed. Ramp to Basement completed.
Utilities: Underground Tank (UGT) Civil Work in Progress
Structural Progress: Structure Completed and Elevation features work in progress.
Gypsum Plaster: Completed up to 18 Floors. Putty one coat completed in 12 Floors.
Flooring Works: Floor Vitrified tiles , Toilet Wall tiles, Toilet Floor tiles completed on 12 Floors and work in progress.
Façade Works: External Glazing in Progress (Framing & Shutters)
Additional Structure: Attached Non-Tower Slab in Progress. Non Tower basement casted.
Basement Access: Ramp down to basement completed.
Structural Milestone: 24th Floor Slab Completed and work in progress at Elevation features.
Internal Finishing: Gypsum Plaster Completed up to 22 Floors. One Coat putty completed in 18 Floors.
Kitchen Works: Counters Completed for 18 floors
Tiling Progress:
• Flooring – up to 21 Floors
• Walls – up to 21 Floors
• Kitchen & Balconies – up to 21 Floors
Façade Works: External Glazing in Progress (Framing & Shutters).
Additional Structure: Attached Non-Tower Slab for Basement completed. Work in progress for Podium slab attached to Tower-M
Utilities: STP Civil Works Completed. UGT civil work completed. Both Ramps to Basement and to Podium completed.
MEP Work: Fire Fighting Work in progress.
Structural Progress: 24th Floor Slab Completed
Façade Works: Elevation Features Completed
Internal Finishing: Gypsum Plaster, Kitchen Counters & Tiling Completed (Flooring, Walls, Kitchen & Balconies). One coat putty completed.
Glazing Works: External Glazing in Progress (Framing & Shutters)
Vertical Transport: Lift Materials Received; Installation in Progress. A
Lift Architraves are being fixed.
Podium Works: Attached Non-Tower Slab & Upstream Ramp Completed.
Common Areas: Corridor Flooring Completed
Staircase Works: Granite Flooring Completed; SS Railing Completed.
Joinery Works: Door Fixing in Progress
Structural Progress: 24th Floor Slab Completed
Façade Works: Elevation Feature Completed; External Glazing in Progress (Framing & Shutters).
Internal Finishing: Gypsum Plaster, Kitchen Counters & Tiling Completed (Flooring, Walls, Kitchens, Toilets & Balconies). One coat Putty completed.
Vertical Transportation: Lift Materials Received; Installation in Progress. Lift Architraves are being fixed.
Podium Works: Attached Non-Tower Slab & Upstream Ramp Completed.
Common Areas: Corridor Flooring Completed.
Staircase Works: Granite Flooring Completed.
Joinery Works: Door Fixing in Progress
Structural Progress: 24th Floor Slab Completed. Elevation features completed.
Internal Finishing: Gypsum Plaster, Kitchen Counters & Tiling Completed (Flooring, Walls, Kitchen & Balconies)
Façade Works: External Glazing in Progress (Framing & Shutters).
Utility Works: UGT Civil Work Completed. Ramp to Basement Completed.
Additional Structure: Attached Non-Tower Slab Work 50% Completed both Basement and Podium..
Common Areas: Corridor Flooring Completed.
Staircase Works: Granite Flooring Completed. SS Railing in Staircase completed.
• 2nd floor slab completed • Brickwork in progress.
• Attached Basement Slab completed.
• Attached Podium Slab completed.
• Swimming Pool walls casted.
Structure: Completion Certificates Received
Finishing: Possession Handed Over
Façade: Completed
Utilities: Operational
Community: 1,500+ Families Now Residing in the Project
🏗 Structure: CC Received
🧱 Finishing: Possession Delivered
🪟 Façade: Completed
⚙ Utilities: Operational
🏢 Community: 1,500+ Families Living & Enjoying the Club
Structure: Occupation Certificate Received
Finishing: Possession Delivered
Façade: Completed
Utilities: Operational
Marketplace: A thriving retail hub now serving the daily needs of residents.
🏗 Structure: CC Received
🧱 Finishing: Possession Delivered
🪟 Façade: Completed
⚙ Utilities: Operational
🏢 Community: 1,000+ Families Living & Enjoying the Club
Structure: Occupation Certificate Received
Finishing: Possession Delivered
Façade: Completed
Utilities: Operational
Marketplace: A thriving retail hub now serving the daily needs of residents.
Structure: Completion Certificates Received
Finishing: Possession Handed Over
Façade: Completed
Utilities: Operational
Retail Experience: Ready to welcome brands, businesses, and visitors.