Official Progress Report

Generated: 29 Oct 2026, 2:29 PM IST

The Brook – Phase 1

Luxury Residences 🏙️

Tower-A

Structure: Structure Completed along with Elevation features. MS railing and Door Frames Completed.

Interior finishes: Gypsum Plaster, POP, Kitchen Counter Fixing, Fire Fighting Pipe covering , Tile laying activities completed. Doors and Locks Installation complete.

Common Areas: Granite Flooring/ Tile Flooring in Corridors and staircases completed, SS railing in staircases installed.

Exterior : MS railing Completed. Texture Painting in progress. External Glazing ( UPVC work) Framing and shutter installed. Plumbing Shaft covering workin progress.

Mep work: Fire Fighting Pipes laid. Rising Mains and Lifts are installed.

External Development: Podium water- proofing completed. Work in progress for various elements related to external Development say Water Body, seating Alcoves etc.

08 Sep 2026
Site photograph — Tower-A

Tower-A

🏗️ Completed Milestones

🧱 Structural & Exterior: The 24th-floor slab, along with the attached non-tower slab, has been successfully cast. All exterior elevation features have now been fully completed.

🏠 Interior Finishes: Gypsum plastering and kitchen counter installations are complete.

Tile laying across general flooring, walls, kitchens, and balconies has been finished, along with the corridor flooring.

🏛️ Common Areas: Granite flooring in the staircases and stainless-steel railings have been fully installed.


🔧 Ongoing Operations

🪟 Exteriors & Logistics: External glazing work is actively underway, currently focusing on framing and shutter installation.

Elevator materials have arrived on site, and installation activities have commenced.

🚿 Plumbing & Carpentry: Installation of plumbing fixtures (sinks and cisterns) and door fittings is currently in progress.

08 Mar 2026
Site photograph — Tower-A

Tower-B

Structure: Structure Completed along with Elevation features. MS railing and Door Frames Completed.

Interior finishes: Gypsum Plaster, POP, Kitchen Counter Fixing, Fire Fighting Pipe covering , Tile laying activities completed. Doors and Locks Installation complete.

Common Areas: Granite Flooring/ Tile Flooring in Corridors and staircases completed, SS railing in staircases installed. Entry lobby work in progress.

Exterior : MS railing Completed. Texture Painting in progress. External Glazing ( UPVC work) Framing and shutter installed. Plumbing Shaft covering work in progress.


MEP work: Fire Fighting Pipes laid. Rising Mains and Lifts are installed. Basement Fire fighting work, GI line work , STP, Fire Fighting work in progress. In Electrical ( External) Transformers, DG sets, HT panel procured and installation in progress. Main LT panel under procurement.


External Development: Podium water- proofing completed. Work in progress for various elements related to external Development say Water Body, seating Alcoves etc.


08 Sep 2026
Site photograph — Tower-B

Tower-B

🏗 Structure: 24th Floor Slab Completed; Attached Non-Tower Slab Completed; Basement Ramp Cast

🧱 Finishing: Gypsum Plaster, Kitchen Counters, Tiling (Flooring, Walls, Kitchens & Balconies), Whitewash, Corridor Flooring & Staircase Granite with SS Railings Completed; Sink & Door Fixing in Progress

🪟 Façade: Elevation Features Completed; External Glazing in Progress (Framing & Shutters)

⚙ Utilities: Earthing Completed; Lift Materials Received & Installation in Progress

🏢 Common Areas: Corridors & Staircases Fully Finished

08 Mar 2026
Site photograph — Tower-B

Tower-C

Structure: Structure Completed along with Elevation features. MS railing and Door Frames Completed.

Interior finishes: Gypsum Plaster, POP, Kitchen Counter Fixing, Fire Fighting Pipe covering , Tile laying activities completed. Doors and Locks Installation complete.

Common Areas: Granite Flooring/ Tile Flooring in Corridors and staircases completed, SS railing in staircases installed. Entry lobby work in progress. VD flooring completed in stilt parking areas. BAsement VD flooring in progress.



Exterior : MS railing Completed. Texture Painting in progress. External Glazing ( UPVC work) Framing and shutter installed. Plumbing Shaft covering in progress.


MEP work: Fire Fighting Pipes laid. Rising Mains and Lifts are being installed. Basement Fire fighting work, GI line work , STP, Fire Fighting work in progress. In Electrical ( External) Transformers, DG sets, HT panel Procured. MAin LT panel Ordered. ESS room completed.

External Development: Podium water- proofing completed. Work in progress for various elements related to external Development say Water Body, seating Alcoves etc. Main Gate structure RCC work cast. ESS Room civil work completed..


08 Sep 2026
Site photograph — Tower-C

Tower-C

Structural Milestone: 24th Floor Slab Completed; Attached Non-Tower Slab Completed; Basement Ramp Cast

Façade Works: Elevation Features Completed; External Glazing (Framing & Shutters) in Progress

Interior Finishing: Gypsum Plaster, Kitchen Counters, Tiling (Flooring, Walls, Kitchens & Balconies) & Whitewash Completed

Services & Utilities: Earthing Completed; Lift Materials Received & Installation Underway

Common Areas: Corridor Flooring Completed; Staircase Granite Flooring with SS Railing Completed

Final Fixtures: Sink Fixing & Door Installation in Progress

08 Mar 2026
Site photograph — Tower-C
Site photograph — Tower-C
Site photograph — Tower-C
Site photograph — Tower-C

Club & Social Spaces 🥂

Paper Boat 🍹

✔️ Superstructure, Plastering & Firefighting Piping— Complete

✔️ Pool Civil Work — Done. Water proofing completed. Pool Tile work in progress. Pool Plant ordered.

🚧 External Glazing & ACP Facade — Completed.

💎 Italian Flooring — 50% Completed. Tile work in progress in Toilets.

✔️Internal Finishing work in progress.


The buniyaad is strong, and the finishing touches are beginning! 🏢

08 Sep 2026
Site photograph — Paper Boat 🍹
27 Jun 2026

Paper Boat 🍹

Superstructure, Plastering & Firefighting — 100% Complete

✔️ Pool Civil Work — Done. MEP work in progress. Tiles under procurement.

🚧 External Glazing & ACP Facade — In Progress. Glass Facade completed.

💎 Italian Flooring —In progress. Tile laying in Toilets in progress.

Wood work / Wall finishes: Wall panelling work commenced.


Daily Convenience Retail 🛒

Brook Arcade

• Civil works completed • Shutters fixed.

• Tile laying completed.

• Sewer LIne in front of Commercial space laid.

• Rain Water Harvesting pits 5 in No Work in progress.

08 Sep 2026
Site photograph — Brook Arcade

The Brook – Phase 2

Luxury Residences 🏙️

08 Sep 2026

Tower-E

• 15th floor slab completed.

• MEP WORK: Internel Plumbing ( CPVC) work in progress.



08 Sep 2026

Tower-F

• 19th floor slab completed.

• POP work in progress at 3rd floor.

• Door Frame fixing in progress.

• MEP work: Internel Plumbing( CPVC ) in progress.

08 Sep 2026

Tower-G

• 27th floor Terrace slab completed. Elevation features work in progress.

• MS Railing work Completed at 20 Floors.

• Door Frames fixing work in progress and completed at 20 Floors.

• Gypsum plaster in progress.

• Firefighting works in progress.

• MEP work: Internel Plumbing ( CPVC Piping) work in progress.

The Rivulet - Phase 1

Daily Convenience Retail 🛒

Rivulet Plaza

• Slab casting completed • Brickwork in progress
20 Jan 2026
Site photograph — Rivulet Plaza

Luxury Residences 🏙️

Tower-K

Structural Progress: 24th Floor Slab Completed. Work in progress at Elevation features.

Gypsum Plaster: Completed up to 18th Floor

Kitchen Counters: Completed up to 15th Floor

Flooring (Vitrified Tiles): Completed up to 20th Floor.

Wall Tiling: Completed up to 20th Floor

Toilet Tiling: Completed up to 20th Floor

External Façade: Glazing Work in Progress (Framing & Shutters)

Additional Structure: Attached Non-Tower Slab in Progress. UGT Civil work Completed. Ramp to Basement completed.

Utilities: Underground Tank (UGT) Civil Work in Progress

08 Sep 2026
Site photograph — Tower-K

Tower-L

Structural Progress: Structure Completed and Elevation features work in progress.

Gypsum Plaster: Completed up to 18 Floors. Putty one coat completed in 12 Floors.

Flooring Works: Floor Vitrified tiles , Toilet Wall tiles, Toilet Floor tiles completed on 12 Floors and work in progress.

Façade Works: External Glazing in Progress (Framing & Shutters)

Additional Structure: Attached Non-Tower Slab in Progress. Non Tower basement casted.

Basement Access: Ramp down to basement completed.

08 Sep 2026
Site photograph — Tower-L

Tower-M

Structural Milestone: 24th Floor Slab Completed and work in progress at Elevation features.

Internal Finishing: Gypsum Plaster Completed up to 22 Floors. One Coat putty completed in 18 Floors.

Kitchen Works: Counters Completed for 18 floors

Tiling Progress:

• Flooring – up to 21 Floors

• Walls – up to 21 Floors

• Kitchen & Balconies – up to 21 Floors

Façade Works: External Glazing in Progress (Framing & Shutters).

Additional Structure: Attached Non-Tower Slab for Basement completed. Work in progress for Podium slab attached to Tower-M

Utilities: STP Civil Works Completed. UGT civil work completed. Both Ramps to Basement and to Podium completed.

MEP Work: Fire Fighting Work in progress.

08 Sep 2026
Site photograph — Tower-M

Tower-S

Structural Progress: 24th Floor Slab Completed

Façade Works: Elevation Features Completed

Internal Finishing: Gypsum Plaster, Kitchen Counters & Tiling Completed (Flooring, Walls, Kitchen & Balconies). One coat putty completed.

Glazing Works: External Glazing in Progress (Framing & Shutters)

Vertical Transport: Lift Materials Received; Installation in Progress. A

Lift Architraves are being fixed.

Podium Works: Attached Non-Tower Slab & Upstream Ramp Completed.

Common Areas: Corridor Flooring Completed

Staircase Works: Granite Flooring Completed; SS Railing Completed.

Joinery Works: Door Fixing in Progress

08 Sep 2026
Site photograph — Tower-S

Tower-T

Structural Progress: 24th Floor Slab Completed

Façade Works: Elevation Feature Completed; External Glazing in Progress (Framing & Shutters).

Internal Finishing: Gypsum Plaster, Kitchen Counters & Tiling Completed (Flooring, Walls, Kitchens, Toilets & Balconies). One coat Putty completed.

Vertical Transportation: Lift Materials Received; Installation in Progress. Lift Architraves are being fixed.

Podium Works: Attached Non-Tower Slab & Upstream Ramp Completed.

Common Areas: Corridor Flooring Completed.

Staircase Works: Granite Flooring Completed.

Joinery Works: Door Fixing in Progress

08 Sep 2026
Site photograph — Tower-T

Tower-U

Structural Progress: 24th Floor Slab Completed. Elevation features completed.

Internal Finishing: Gypsum Plaster, Kitchen Counters & Tiling Completed (Flooring, Walls, Kitchen & Balconies)

Façade Works: External Glazing in Progress (Framing & Shutters).

Utility Works: UGT Civil Work Completed. Ramp to Basement Completed.

Additional Structure: Attached Non-Tower Slab Work 50% Completed both Basement and Podium..

Common Areas: Corridor Flooring Completed.

Staircase Works: Granite Flooring Completed. SS Railing in Staircase completed.

08 Sep 2026
Site photograph — Tower-U

Club & Social Spaces 🥂

Pebble Castle🎯

• 2nd floor slab completed • Brickwork in progress.

• Attached Basement Slab completed.

• Attached Podium Slab completed.

• Swimming Pool walls casted.


08 Sep 2026
Site photograph — Pebble Castle🎯

Fusion Homes

Luxury Residences 🏙️

Tower A~L

Structure: Completion Certificates Received

Finishing: Possession Handed Over

Façade: Completed

Utilities: Operational

Community: 1,500+ Families Now Residing in the Project

01 Jan 2018
Site photograph — Tower A~L

Club & Social Spaces 🥂

Club Fusion 🏛️✨

🏗 Structure: CC Received

🧱 Finishing: Possession Delivered

🪟 Façade: Completed

⚙ Utilities: Operational

🏢 Community: 1,500+ Families Living & Enjoying the Club

01 Jan 2018
Site photograph — Club Fusion 🏛️✨

Daily Convenience Retail 🛒

Fusion Bazaar

Structure: Occupation Certificate Received

Finishing: Possession Delivered

Façade: Completed

Utilities: Operational

Marketplace: A thriving retail hub now serving the daily needs of residents.

01 Jan 2018
Site photograph — Fusion Bazaar

French Apartments

Club & Social Spaces 🥂

French Club 🍷🗼✨

🏗 Structure: CC Received

🧱 Finishing: Possession Delivered

🪟 Façade: Completed

⚙ Utilities: Operational

🏢 Community: 1,000+ Families Living & Enjoying the Club

01 Jan 2019
Site photograph — French Club 🍷🗼✨

Daily Convenience Retail 🛒

French Arcade

Structure: Occupation Certificate Received

Finishing: Possession Delivered

Façade: Completed

Utilities: Operational

Marketplace: A thriving retail hub now serving the daily needs of residents.

01 Jan 2019
Site photograph — French Arcade

U:Fairia

Commercial Hub 🏬

Retail Outlets | Office Spaces | Studio Units | Multiplex | Food Court

Structure: Completion Certificates Received

Finishing: Possession Handed Over

Façade: Completed

Utilities: Operational

Retail Experience: Ready to welcome brands, businesses, and visitors.

01 Apr 2024
Site photograph — Retail Outlets | Office Spaces | Studio Units | Multiplex | Food Court
Site photograph — Retail Outlets | Office Spaces | Studio Units | Multiplex | Food Court